November 8, 2024:

For the last two days the construction workers have been placing the foundation and concrete for the downstairs classrooms and today walling of the classes, the kitchen and dining hall has begun.   Starting Monday, the workers will begin constructing the concrete slab for the upstairs classes and lab and begin walling of the upstairs classes and lab.

 

 

November 11, 2024

The weekend has been very busy at Spring Valley as the construction workers completed the walling of the downstairs classes. Today the workers began placing the wood frame work and concrete on the pillars that will hold the upstairs classrooms and a lot of construction material has been delivered to the school. The construction is also serving as means of inspiration and motivation for the children as they watch the walls going up!